THE WIRE · UPDATED 2:48 AM MST No story is too small.
NewsOgden

Ogden water line project at Pineview Reservoir may finish early

Utah.News 1 source cited Details

How this story was published

Published automatically from one public source cited; not yet reviewed by the desk. Tell us if something is wrong ↗

Source

standard.net

Utah.News publishes every story with the sources it was built from. Questions or a correction: corrections@utah.news.

AI-written from public sources Written by Utah News AI and quality-checked before publishing.
Ogden water line project at Pineview Reservoir may finish early
Photo via standard.net
The project to replace Ogden's 36-inch water line across the Pineview Reservoir lakebed may conclude next month. Officials stated on Thursday, Nov. 12, 2026, that the project is currently ahead of its Jan. 1, 2027, deadline.

Key takeaways

  • The water line replacement project at Pineview Reservoir is ahead of its Jan. 1, 2027, deadline.
  • Ogden City and the DNR are collaborating on lake remediation and fish habitat installation.
  • The Port Ramp Marina is scheduled to be completely replaced through agency collaboration.
  • Work will continue in Ogden Canyon over the next two years following the reservoir phase.

The project to replace Ogden's aging 36-inch water line across the Pineview Reservoir lakebed may conclude next month. On Thursday, Nov. 12, 2026, Ogden City and other entities met at the city's well fields on the shore of Pineview Reservoir to discuss the project's status.

Ogden City Public Services Executive Director Justin Anderson reported that the project is progressing smoothly and is currently ahead of its Jan. 1, 2027, deadline. The work involves installing a new 48-inch line and slip-lining a 32-inch HDPE line into the existing pipe to provide redundancy and additional water flow. A temporary bypass line is currently feeding Ogden City residents.

The project includes collaboration between Ogden City, the state, and the Forest Service to remediate the lake as it refills. Ogden City is contributing $200,000 toward the effort, while the DNR is contributing $50,000. The DNR and the city plan to install approximately 1,300 large fish structures on the reservoir bottom at depths of 40 to 50 feet to serve as nursery and cover habitat for small fish and attractors for larger fish.

Another collaborative effort involves the complete replacement of the Port Ramp Marina. Ashley Klase, an Ogden District ranger with the U.S. Forest Service, noted that the project follows a large construction project for a new point day use site and updates to traffic patterns.

Following the completion of the Pineview Reservoir phase, the project will continue over the next couple of years in Ogden Canyon.

For more information and updates on the project, visit https://ogdencitypipeline.com/

Watch

Utah News

Article details

CategoryNews
CityOgden
ToneNeutral
ProductionAI Generated
Report a problem with this story
What's off? Pick any that fit, or just write below.

Every report is read and checked against the story's sources. Your email, if you give one, is used only to contact you about this message and is never shown publicly. Please keep other personal details out of the text. Privacy