Provo Airport expansion: Three gates expected by 2027, full completion by 2029

Utah.News 1 source cited Details

How this story was published

Published automatically from one public source cited; not yet reviewed by the desk. Tell us if something is wrong ↗

Source

heraldextra.com

Utah.News publishes every story with the sources it was built from. Questions or a correction: corrections@utah.news.

AI-written from public sources Written by Utah News AI and quality-checked before publishing.
Provo Airport expansion: Three gates expected by 2027, full completion by 2029
Photo via heraldextra.com
The Provo Airport expansion is making progress with three new gates expected to open in 2027 and full project completion scheduled for 2029. The airport is on track to reach a record 1.25 million passengers in 2026 as construction continues on multiple phases.

Key takeaways

  • Provo Airport is on track for 1.25 million passengers in 2026.
  • The $160 million expansion project is scheduled for full completion in 2029.
  • Three new gates in the north expansion are expected to open before Thanksgiving 2027.
  • Phase four construction is expected to begin in spring 2028.

The Provo Airport is experiencing significant growth in passenger volume and infrastructure development, according to a November 20 report. The transportation hub is on track to serve a record 1.25 million passengers in 2026 while construction on phases two and three of a projected $160 million expansion continues.

The four-phase expansion project, which began in 2025, is scheduled to be fully completed in 2029. Once finished, the project will expand the airport to 10 gates, transform baggage and ticketing areas, and pave the full airport parking lot.

Airport Director Brian Torgersen stated that the project's estimated $130 million price tag set in 2025 has increased by $30 million due to rising labor and material costs. This cost increase has slightly delayed phase four, which involves expanding the south side of the airport and is currently in the design phase. The airport hopes to begin construction on phase four in spring 2028.

Current construction progress includes phase two and phase three. Phase two, which involves ticket counter expansions, baggage handling, and baggage screening, is expected to have its first parts open in spring 2027.

Phase three, involving the expansion of the terminal to the north, recently reached a milestone with the placement of a final steel beam. Torgersen said the first three gates on the north expansion should be open before Thanksgiving 2027. This opening is expected to allow the airport to remove temporary holdroom space currently located outside the main terminal.

Funding for the expansion is provided by various entities, including $78 million from Utah County’s TRCC funds. Additional support comes from the FAA, the state of Utah, Provo, and the Mountainland Association of Governments.

While the airport reaches full capacity three times a day—early morning, midday, and late at night—Torgersen noted there is often space in the mid-morning and late afternoon that can be filled. The airport is currently speaking with existing and new airlines about filling these gaps to utilize more desirable departure times.

The airport is also under contract with a contractor to begin parking lot construction, with a goal of completing the work by late summer or fall 2027.

Watch

Utah News

Article details

CategoryNews
CityProvo
ToneNeutral
ProductionAI Generated
Report a problem with this story
What's off? Pick any that fit, or just write below.

Every report is read and checked against the story's sources. Your email, if you give one, is used only to contact you about this message and is never shown publicly. Please keep other personal details out of the text. Privacy