The South Weber City Council passed a resolution on November 17, 2026, awarding the West Reservoir Drain Line Project contract to Saunders Excavation, according to a November 18 report.
The project was initiated after the drain line for the west reservoir became disconnected, which created a large hole and exposed an old ductile iron water transmission line and vault drain.
Requests for bids for the project were advertised on October 16, 2026, and opened on November 3, 2026. Nine bids were received and evaluated by City Engineer Jones Civil, which included reference checks on the low bidder.