The St. George City Council was scheduled to consider a proposal to lift a temporary pause on new blasting permit requests during its meeting on Thursday, November 19, 2026. The council was set to vote on Ordinance 2026 089, which would repeal the current moratorium.
The temporary pause on new blasting permit requests applied to applications submitted on or after October 2, 2026. This rule was adopted by the council on October 1, 2026, via Ordinance 2026 079, following public feedback regarding blasting, documentation, notice, and enforcement. While the moratorium could have remained in place for up to six months, the council maintained the ability to end it sooner. Existing permittees were excluded from the temporary pause according to the city attorney's recorded explanation during the October meeting.
City staff indicated that the pause was no longer needed following feedback from a council work meeting held on November 5, 2026. During that meeting, officials discussed several topics including neighborhood notice, signage, mapping accuracy, independent monitoring, recordkeeping, enforcement, site verification, training, and the assignment of responsibility among city departments. The proposed repeal does not include revised blasting standards, meaning residents would need to monitor whether the city brings proposed changes back for a future meeting.
The current blasting standards, adopted in July 2025, require permit applications at least five business days before blasting begins and limit permits to licensed operators. The rules state that buildings that could have occupants within one thousand feet must receive notice at least three days before operations begin. Additionally, contractors must offer a survey at no cost to owners of buildings within three hundred feet. Permits can last up to 180 days, with one possible 90-day extension, and the fire chief or a designee may suspend or revoke a permit for violations or imminent public hazards.
A repeal of the moratorium would allow permit processing to resume but would not erase existing permit, notice, monitoring, and safety requirements. The agenda for the November 19, 2026, meeting did not include an engineering finding regarding specific structural damage or a proposal to end all city rules applying to blasting.