Lehi transitions to restoration phase of secondary water meter program

Correction

This article was revised after a reader report. Corrected July 17, 2026 · 38 days ago

Official source This story comes from an official government or institutional source. How it was made ↓
A close-up of municipal financial documents and irrigation hardware on a desk, symbolizing Lehi's transition from water meter installation to new rate structures and drought management planning.
Photo via AI illustration
Lehi is moving from the construction phase of its state-mandated secondary water meter program into a period focused on landscaping restoration and drought management. While most meter installations are complete, city officials continue to work on developing a new usage-based rate structure for residents.

Key takeaways

  • Lehi is transitioning from meter installation to landscaping restoration and rate development.
  • The program is part of a state mandate requiring all pressurized connections to be metered by 2030.
  • A multi-year rate study is being conducted to move from flat lot-size charges to usage-based billing.
  • Current irrigation use is down roughly 18% for the season, aiding drought management efforts.

Lehi’s state-mandated secondary water metering program has transitioned from a multi-year construction campaign into a phase focused on completing remaining installations, repairing disturbed landscaping, and determining a new usage-based rate structure. The project, driven by House Bill 242, requires secondary water suppliers to meter pressurized connections by January 1, 2030.

The local program is a five- to six-year retrofit of more than 12,000 meters that launched in October 2022. City officials expect a 20% to 40% drop in outdoor water use once usage data is available to residents. The project was funded through a $10 million state grant, a $3,643,000 loan from the Utah Division of Water Resources at 1% interest, and approximately $643,000 from the city budget.

Hydro Vac Excavations LLC was contracted for the installations. While phases 1 through 9 and portions of phase 10 are complete, the project has moved toward restoration efforts, including sod replacement at roughly 4,000 locations. Some residents have reported issues such as settling soil and uneven patches near new meter lids.

Regarding future costs, a multi-year rate study is underway to decide how residents will pay for pressurized irrigation by the gallon rather than a flat lot-size charge. While the city is reviewing models from peer systems like Alpine, Saratoga Springs, Spanish Fork, and Springville, officials stated that any new structure would be adopted after a transparent process with public comment.

Drought management is already utilizing the meters as a planning tool. As of July 16, 2026, irrigation use was reported to be down about 18% for the current season, which has reduced the near-term risk of moving to a more restrictive phase of the Water Shortage Management Plan. The city's long-term goal is to reduce secondary water use from approximately 161 gallons per capita per day in 2024 to about 145 by 2030.

How this story was made

Corroborated by 7 independent sources

Utah News confirmed this story across multiple independent newsrooms before publishing.