THE WIRE · UPDATED 7:55 PM MST No story is too small.
NewsWest Jordan

West Jordan High School crews complete key milestones of Phase 1

Utah.News 1 source cited 1 primary Primary: jordandistrict.org Details

How this story was published

Published automatically from one public source cited; not yet reviewed by the desk. Tell us if something is wrong ↗

Primary source

jordandistrict.org — an official government, school or university source.

Utah.News publishes every story with the sources it was built from. Questions or a correction: corrections@utah.news.

AI-written from public sources Written by Utah News AI and quality-checked before publishing.
West Jordan High School crews complete key milestones of Phase 1
Photo via jordandistrict.org
Construction crews at West Jordan High School are making progress on a renovation project, with Phase 1 expected to finish in late spring 2027. The project involves remodeling the 45-year-old building to improve accessibility and facilities.

Key takeaways

  • Phase 1 of the West Jordan High School renovation is on track for completion in late spring 2027.
  • Workers have completed raising the commons area floor and installed support beams for Phase 2.
  • The project involves expanding the gymnasium footprint and adding five career and technical education classrooms.
  • The remodel is expected to save taxpayers over $100 million compared to a full rebuild.
  • Final completion for the entire project is set for November 2029.

Construction crews at West Jordan High School are making steady progress on a major renovation project and are on track to complete Phase 1 in late spring 2027, according to a November 9 statement from the Jordan School District.

Crews have already completed raising the floor in the commons area and installed key support beams designed to lift the roof during Phase 2. Around the gymnasium, workers have begun tearing down the east wall and building new structural walls to expand the gym footprint to the east.

Meanwhile, the southwest corner of the building remains closed off while workers remodel classrooms on both the first and second floors. Construction is also underway to add five career and technical education classrooms to the west side of the building.

The extensive renovation of the 45-year-old building began this summer following approval from the Jordan Board of Education. Opting for a comprehensive remodel rather than a full rebuild is expected to save taxpayers more than $100 million.

Set for final completion in November 2029, the modernized facility will feature more natural light, improved ADA accessibility, new flooring, collaborative learning spaces, a new dance studio, an upgraded weight room, and an expanded gym.

Article details

CategoryNews
CityWest Jordan
ToneNeutral
ProductionAI Generated
Report a problem with this story
What's off? Pick any that fit, or just write below.

Every report is read and checked against the story's sources. Your email, if you give one, is used only to contact you about this message and is never shown publicly. Please keep other personal details out of the text. Privacy