George Washington Blvd
Bridge Construction
Project Overview
The George Washington Bridge Project will construct a new bridge connecting
George Washington Blvd to Crosby Way. The project is designed to improve
regional connectivity in the cities of St. George and Washington, as well as to
reduce existing and future delays at key intersections. Improvements began in
February 2026 and will be completed in July 2027.*
Project Update | October 2
Work, Work, Work
Our team is busily making preparations for the final three deck pours in the
middle of October.
Various activities include:
Forming the deck for spans four, five and six
Tying rebar on these same spans
Framing the bridge overhangs
Finishing the rip rap placement
Grading around the bridge embankment.
Looking forward to another busy week with a forecast of blue sky and
sunshine.
*Schedule is subject to weather and other unforeseen circumstances.
Top Photo: Our new bridge rises off the desert floor at an average height of 30
feet in the air.
Bottom Photo: The green glow of rebar is moving closer to the east end of the
bridge as our team makes steady progress.
Materials continue to be brought onto the project site from Crosby Way.
All users of the Virgin River Trail need to stop at the designated stop
signs to allow safe passage for equipment and users. We appreciate
your patience and help in maintaining a safe environment.
Video footage from October 1
Timeline
*Schedule is subject to weather and other unforeseen circumstances.
Hotline/Cell/Text | Lisa Beck, Public Information Contact | (435) 531-1358
https://sgcityutah.gov/gwbridge/
A City of St. George Public Works Project