Project Overview Salt Lake City Department of Public Utilities (SLCDPU) provides drinking water to more than 365,000 residents. The 4th Avenue Well, located near 4th Avenue and Canyon Road, is one of the City’s largest groundwater sources. In 2023, PFAS compounds were detected in

Project Overview

Salt Lake City Department of Public Utilities (SLCDPU) provides drinking water to more than 365,000 residents. The 4th Avenue Well, located near 4th Avenue and Canyon Road, is one of the City’s largest groundwater sources.

In 2023, PFAS compounds were detected in the 4th Avenue Well, and the well was taken offline out of caution. SLCDPU is conducting a multi-phase project to evaluate treatment and restoration options.

Construction Impacts

Typical construction impacts such as noise, dust, and vibration during working hours

Temporary traffic restrictions and closures along 4th Avenue

Clearly marked detours and traffic control

Current Construction Activities (May 2026):

Reinstallation of the well pump that was removed during earlier testing

Cleaning of the well using a “brush and bail” process to remove sediment buildup

Restarting the well under normal operating conditions for additional water quality testing

Temporary traffic restrictions and closures near the south side of the well to allow equipment access

Clearly marked traffic control to maintain safety for residents and visitors

Why is this work being done?

Initial testing completed in December 2025 did not produce conclusive results, likely because the well was not actively operating at the time.

This next phase of work will allow the City to:

Evaluate PFAS levels while the well is running under normal conditions

Collect more accurate and representative water quality data

Better understand how the well may be safely used in the future

The results will help guide decisions about the long-term future of the 4th Avenue Well.

Recent Construction Activities (Winter 2025):

The team conducted flow and velocity measurements to create a profile that will inform water quality sampling.

Teams used this profile to create a mass balance of the well.

Why is this work happening now?

This work is investigative. A specialized team will take water samples from different depths in the well to understand:

How PFAS is moving in the aquifer

Working to identify the source of PFAS

Whether only certain layers are affected

Whether the well could be modified to avoid PFAS, or if a new well may be needed

Restoring high-quality and reliable water supply takes careful planning.

This phase helps the City determine:

Whether the well can be restored without PFAS

Whether treatment is needed

Or whether a new well location should be developed

Doing this work now helps protect long-term water supply reliability.

Frequently Asked Questions

What is the 4th Avenue Well and why is it important?

The 4th Avenue Well is one of Salt Lake City’s key groundwater sources. It usually operates during the summer to help meet higher water demand and maintain reliable water pressure in the downtown and Capitol Hill areas. When active, it can supply up to 6 million gallons of drinking water per day.

What are PFAS and why is this well offline?

PFAS (short for per- and polyfluoroalkyl substances) are a group of man-made chemicals used in products like firefighting foam, stain-resistant fabrics, and nonstick coatings. These chemicals are widespread in the environment and are being detected in many water sources nationwide.

During routine federal testing in 2023, PFAS were detected in the water from the 4th Avenue Well at levels above new EPA drinking water standards. As a result, SLCDPU took the well offline.

This means no PFAS-impacted water is being delivered to customers.

Is my drinking water safe?

Yes. Salt Lake City continues to meet all state and federal drinking water standards. The 4th Avenue Well is not currently in use.

What work is happening now?

The current work is investigative. A specialized team will take water samples from different depths in the well to understand:

How PFAS is moving in the aquifer

Working to identify the source of PFAS

Whether only certain layers are affected

Whether the well could be modified to avoid PFAS, or if a new well may be needed

The results will help the City choose the best long-term solution.

Will there be construction impacts?

Yes — temporarily.

During the roughly five-week field work period, neighbors may see:

Construction vehicles and crews

A fenced work zone

Temporary lane and sidewalk closures

Normal construction noise during daytime working hours

This work does not involve major excavation or new above-ground structures.

How long will this phase last?

Approximately five weeks, scheduled for late fall/early winter 2025.

The City will share exact dates before work begins.

Why is the City doing this now?

Restoring high-quality and reliable water supply takes careful planning.

This phase helps the City determine:

Whether the well can be restored without PFAS

Whether treatment is needed

Or whether a new well location should be developed

Doing this work now helps protect long-term water supply reliability.

How is this different from the 2019 well upgrade project?

We recognize there was strong public concern during the 2019 project.

This current work is different in key ways:

2019 Project

Permanent pump house construction

Major above-ground structure changes

Longer construction duration

Designed to update electrical and mechanical systems

Current PFAS Work

Temporary investigate work

No new structure being built

~5 weeks total

Designed to protect long-term water quality

We are committed to being proactive, transparent, and respectful in how we communicate throughout this effort.

How can I get project updates or ask questions?

Project Email: 4thavewell@slc.gov

Project Hotline: 801-616-3336

Project updates will also be shared:

On the SLCDPU website

SLCDPU social media channels (Connect with us on Instagram and Facebook)

How will the City use community feedback?

Because this phase is investigative, public input does not determine whether the sampling work occurs, but feedback can and will help shape:

How we communicate impacts

What information we emphasize in updates

How we talk about the long-term mitigation plan

Related

Water Quality FAQ

Interview with SLCDPU Director Laura Briefer

Contact

Call 801-616-3336

Email 4thavewell@slc.gov

To sign up for regular email updates about this project, send an email to 4thAveWell@slc.gov with “Updates” in the subject line.

Timeline

Work began May 11 and is expected to continue through May 19.