Responsive Margin
Roadway and irrigation improvements
This map shows project boundaries in yellow, accessible areas in blue, accessible by foot areas in purple and closed areas in red.
Project overview
The City Cemetery is generally between 11th Avenue and 4th Avenue, North Street and U Street. The project area is in the Cemetery’s northeast quadrant, generally located between 1040 East and 1200 East and 280 North and 11th Avenue
Project updates
April 2026
The Salt Lake City Cemetery Roadway and Irrigation Improvements project managers have continued to check things off the project list!
Sod and turf are continuing to be corrected
Concrete remediation continues with panel and curb replacement
Saddle and swing joint replacement as been completed
MC Green (landscaping) turf and sod remediation is ongoing. Additional adjustments and remediation to resume after Memorial Day
Bond funds were spent before the deadline of March 31, 2026
Sod and turf areas are still being patched!
Turf remediation
Concrete remediation
Curb replacement
Completed curb
Concrete panel replacement
Overall project schedule
December 2024 – July 2026
Construction began December 2024, with some mobilization beginning November 25-27, 2024.
The estimated completion date of work sequence one (about 80% of the work) is winter 2025.
The estimated completion of work sequence two is summer 2026.
Anticipated hours of operation will generally be 7 a.m. to 6 p.m. Monday through Friday and Saturday 7 a.m. to 2 p.m.
*Schedule is subject to change depending on weather, permitting, and unknown circumstances.
General project description
Tree protection and SWPPP, demolition, utilities (roadway irrigation and plat irrigation), grading, curb and gutter, concrete paving, landscape restoration.
Roadway improvements generally include replacing exiting roadway features with concrete pavement, curb and gutter, waterways, and street signs with decorative posts.
Roadway area irrigation system improvements (roadway and roadway vaults and associated assemblies and electrical pipe, wiring, and controllers) generally include replacing irrigation with new irrigation system.
Plat area irrigation system improvements generally include replace landscape irrigation and install new root watering system for trees, and related work.
Contact us
Phone: 385-530-5790
Construction Project Manager: Hayden Barker
Cemetery website
Have an issue? Report or request on mySLC