THE WIRE · UPDATED 7:05 AM MDT No story is too small.
Official SourceSt. GeorgeVirgin

Email from Harmony Public Involvement

Utah.News 1 source cited 1 primary Primary: sgcityutah.gov Details

How this story was published

Published automatically from one public source cited; not yet reviewed by the desk. Tell us if something is wrong ↗

Primary source

sgcityutah.gov — an official government, school or university source.

Utah.News publishes every story with the sources it was built from. Questions or a correction: corrections@utah.news.

Official source This story comes from an official government or institutional source.
A technical architectural blueprint of a bridge structure lies on a wooden desk next to a drafting compass, with Utah's red rock landscape visible through a window in the background.
Photo via AI illustration
George Washington Blvd Bridge Construction Project Overview The George Washington Bridge Project will construct a new bridge connecting George Washington Blvd to Crosby Way.

George Washington Blvd

Bridge Construction

Project Overview

The George Washington Bridge Project will construct a new bridge connecting

George Washington Blvd to Crosby Way. The project is designed to improve

regional connectivity in the cities of St. George and Washington, as well as to

reduce existing and future delays at key intersections. Improvements began in

February 2026 and will be completed in Summer 2027.*

Project Update | September 4

40% FINISHED!

Our project is 40% complete and no thanks to ‘Mother Nature’ who

continues to swell the Virgin River leaving a large debris field every time. It

takes our team a few days to clean up. That being said, we are still on

schedule.

This weekend could be another storm event. Please stay out of the Virgin

River in our construction zone. High water events are dangerous, and the

river is closed through our site.

Our reinforcing ironworkers continue to tie coated rebar into place on deck

spans one, two and three. They will complete this phase on Wednesday, and

the deck on these three spans will be poured Wednesday, Thursday and

Friday. Our skilled ironworkers will then move to deck spans four, five and six.

The structural work of installing stabilizing diaphragms between

the fifth set of girders is finished, and we are installing these between the

sixth set of girders.

The forming of the overhangs along the edge of the bridge continues for

several weeks.

Work on the project will be suspended from Friday, September 4 at noon

through Monday, September 7 in observance of the Labor Day Holiday.

*Schedule is subject to weather and other unforeseen circumstances.

Top Photo: The green rebar illuminates in the morning sun. This structural

component is key to the strength of our bridge deck.

Middle Photo: Our aggregate team rough grades material around the future

pedestrian tunnel connecting it to the overall bridge.

Bottom Photo: The last eight girders are prepped for installation of deck

panels.

Materials continue to be brought onto the project site from Crosby Way.

All users of the Virgin River Trail need to stop at the designated stop

signs to allow safe passage for equipment and users. We appreciate

your patience and help in maintaining a safe environment.

Video footage from September 3

Timeline

*Schedule is subject to weather and other unforeseen circumstances.

Hotline/Cell/Text | Lisa Beck, Public Information Contact | (435) 531-1358

https://sgcityutah.gov/gwbridge/

A City of St. George Public Works Project

Harmony Public Involvement | PO Box 814 | New Harmony, UT 84757 US

Unsubscribe | Update Profile | Constant Contact Data Notice

Article details

CategoryOfficial Source
CitySt. George, Virgin
ToneNeutral