Crews worked on the north side of 200 North between 500 East and 750 East for paving preparations and pavement application on August 31 and September 1.
Work included preparing the north side of the road and placing the first layer of pavement on September 1.
During the preparation phase on August 31, residents on the north side of 200 North maintained driveway access, although brief interruptions occurred as construction equipment passed in front of driveways. Side streets remained open except for short periods when equipment crossed an intersection.
When crews placed the first layer of pavement on September 1, driveways on the north side of 200 North were not accessible during paving operations.