Crews are scheduled to place the final layer of pavement on 200 North from Fairfield Road to 750 East as part of the 200 North Reconstruction and Utilities Project. The paving work is scheduled for September 4 and September 8 through September 10.
Paving operations are scheduled to occur from 7:00 a.m. to 7:00 p.m. each day, with work occurring on one side of the roadway at a time.
On Friday, September 4 and Tuesday, September 8, crews will pave the north side of 200 North. During this time, traffic will shift to the south side of the roadway, and homes on the north side will not have driveway access. North-side streets at 300 East, 400 East, 500 East, 600 East, and 700 East will be closed at 200 North. Vehicles traveling north will be detoured via Fairfield Road and 750 East.
On Wednesday, September 9 and Thursday, September 10, crews will pave the south side of 200 North. During these operations, traffic will shift to the north side of the roadway, and homes on the south side will not have driveway access. South-side streets at 200 East, 300 East, 400 East, 500 East, and 600 East will be closed at 200 North. Vehicles needing to travel south from 200 North will be detoured via 100 East.
Residents and motorists are encouraged to plan ahead, follow posted detours, and use caution when traveling through the construction area.