SERWTP Projects - Addendum 01.docx ADDENDUM NO. 01 TO THE SERWTP Filter Gallery & Actiflo Building Improvements AT 11574 Wyndcastle Drive Current Bid Submittal Deadline: 2:00 p.m., Tuesday, August 25, 2026 Proposed Change to: 2:00 p.m.

SERWTP Projects - Addendum 01.docx

ADDENDUM NO. 01

TO THE

SERWTP Filter Gallery & Actiflo Building Improvements

AT

11574 Wyndcastle Drive

Current Bid Submittal Deadline: 2:00 p.m., Tuesday, August 25, 2026

Proposed Change to: 2:00 p.m., Thursday, August 27, 2026

FOR

Jordan Valley Water Conservancy District

Kevin Rubow & Adam Cossey

Prepared by

McNeil Engineering - Consulting

This addendum issued the 24th day of August 2026 is for all persons preparing bids for the

above named project, and as such, shall be made a part of the contract documents.

The addendum consists of this cover sheet, 1 page of comments, and a revised Bid

Schedule (5 pages). All changes, corrections, deletions, and/or additions to the initial bidding

documents enumerated herein shall be included in the bidders proposal. In case of any conflict,

this addendum shall govern.

Acknowledgment of receipt of this addendum shall be marked in the appropriate place

on the bid proposal form.

This addendum is to be attached to and is to become a part of the specification covering

the above noted projects, and the said specification is to apply insofar as consistent with the

items hereafter noted:

SERWTP Projects - Addendum 01.docx

Conditions of the Contract:

ITEM 1: Contractors are to discard previous Bid Schedule and use the attached, revised Bid

Schedule with their bids.

ITEM 2: Bid Due Date has been moved to 2:00 p.m., Thursday, August 27, 2026. Any final

questions or approvals for alternates are required by end of business today (24

August 2026). A final addendum, is required, will be issued first thing tomorrow

morning (25 August 2026).

Previous Addendum:

ITEM 3: N/A

Specifications:

ITEM 4: Add dust protection system. Section 01 5616 - Contractor is to provide a dust and

debris contamination prevention system to protect exposed water basins from

construction waste and debris in both the Filter Gallery and the Actiflo buildings.

Contractors are to provide a TuffWrap - SmartSeam system or an approved equal.

https://www.tuffwrap.com/services/suspended-cover/smartseam/

1-800-995-4556.

Drawings and Scope of Work:

ITEM 5: Contractor is to include in their bid repairs to the ceiling in the Filter Gallery along

the length of the new storefront window system in the office area. Include

repainting the entire ceiling from wall to wall.

ITEM 6: Contractor is to include the refinishing of the interior walls behind the clerestory

window replacements in the Filter Gallery and Actiflo buildings. 5/8” water-

resistant gypsum board over 4 mil air barrier and paint the entire wall from corner

to corner.

BID

C-1 (Addendum #1)

BID TO: JORDAN VALLEY WATER CONSERVANCY DISTRICT

The undersigned Bidder hereby proposes to furnish all plant machinery, labor, services,

materials, equipment, tools, supplies, transportation, utilities, and all other items and

facilities necessary to perform all work required under the Bidding Schedule of the

Owner's Contract Documents entitled “SERWTP Filter Gallery & Actiflo Building

Improvements” drawings and all addenda issued by said Owner prior to opening of the

bids.

Addenda, if issued, are only delivered by e-mail to those on Owner’s website

(jvwcd.gov) Plan Holders List.

The undersigned bidder acknowledges receipt of the following addenda:

No. Date Received No. Date Received

Bidder agrees that, within 10 calendar days after receipt of Notice of Award from Owner,

he will execute the Agreement in the required form, of which the Notice Inviting Bids,

Instructions to Bidders, Bid, Information Required of Bidder, Technical Specifications,

Drawings, and all addenda issued by Owner prior to the opening of bids, are a part, and

will secure the required insurance and bonds and furnish the required insurance

certificates; and that upon failure to do so within said time, then the bid guarantee

furnished by Bidder shall be forfeited to Owner as liquidated damages for such failure;

provided, that if Bidder shall execute the Agreement, secure the required insurance and

bonds, and furnish the required insurance certificates within said time, his check, if

furnished, shall be returned to him within five days thereafter, and the bid bond, if

furnished, shall become void. It is further understood that this bid may not be withdrawn

for a period of 45 days after the date set for the opening thereof, unless otherwise required

by law.

Dated: ____________________ Bidder: _______________________________

By: __________________________________

(Signature)

Title: _________________________________

Bidder further agrees to complete all work required within the time stipulated in the

Contract Documents, and to accept in full payment therefore the price(s) named in the

above-mentioned Bidding Schedule(s).

BID

C-2 (Addendum #1)

BID SCHEDULE

Item

No. ITEM QTY UNIT UNIT

COST TOTAL

ACTIFLO BUILDING

1

Remove existing fascia, drip

edge, termination metal, etc.

where new roofing occurs

395 Lin Ft $ $

2

Remove existing concrete tile

roofing, penetration flashing, felts

etc. where new roofing occurs

7,910 Sq Ft $ $

3 Remove existing skylights 2 Ea $ $

4 Remove existing storefront

windows 6 Ea $ $

5

Saw cut and remove and replace

existing hardscape where bubbler

and storm drain system occur

160 Sq Ft $ $

6

Install new 24 ga. pre-finished

metal rain gutter per plan and

spec

330 Lin Ft $ $

7

Install new 24 ga. pre-finished

metal downspouts per plan and

spec

45 Lin Ft $ $

8 Install new bubbler for storm

water per plan and spec 2 Ea $ $

9 Install new SDR-35 storm drain

per plan and spec 160 Lin Ft $ $

10 Install new standing seam metal

roofing system per plan and spec 7,905 Sq Ft $ $

11 Install new 24 ga. Pre-finished

drip edge metal 395 Lin Ft $ $

12 Install new 12" strip of secondary

underlayment per plan and spec 395 Lin Ft $ $

13 Install new 9" strip of secondary

underlayment per plan and spec 110 Lin Ft $ $

14 Install new 24 ga. Pre-finished

metal valleys per plan and spec 110 Lin Ft $ $

15 Install new 24 ga. pre-finished

metal fascia per plan and spec 395 Lin Ft $ $

16 Install new roof hatch per plan

and spec 2 Ea $ $

17 Install new vertical corrugated

metal siding per plan and spec 645 Sq Ft $ $

18 Install new storefront windows

per plan and spec 6 Ea $ $

19 Install galvanized metal pipe jack

flashings per plan and spec 1 Ea $ $

BID

C-3 (Addendum #1)

Item

No. ITEM QTY UNIT UNIT

COST TOTAL

20

Repair and install new gypsum

board over air barrier and paint

on interior wall behind new

clerestory storefront windows

(Add #1 – new bid item)

650 Sq Ft $ $

ACTIFLO BLDG. SUBTOTAL: $

FILTER GALLERY BUILDING

1 Remove existing shingles roofing

system per plan 1 Lump

Sum $

2

Remove existing metal cladding

in locations where new metal

cladding will be installed

1,865 Sq Ft $ $

3

Remove existing fascia system in

locations where new fascia will

be installed

475 Lin Ft $ $

4

Remove existing storefront

window system in locations

where new storefront windows

will be installed

10 Ea $ $

5 Remove existing gypsum ceiling

in locations where damaged 295 Sq Ft $ $

6

Remove metal parapet wall caps

in locations where new metal

parapet will be installed

85 Lin Ft $ $

7

Remove existing landscaping

where bubbler and storm drain

system occurs

90 Lin Ft $ $

8 Repair existing shingle roof per

plan and spec 1 Lump

Sum $

9 Install new metal cladding per

plan and spec 1,865 Sq Ft $ $

10 Install new metal fascia per plan

and spec 475 Lin Ft $ $

11 Install new storefront windows

per plan and spec 10 Ea $ $

12

Install new 24 ga. pre-finished

metal drip edge per plan and

spec

475 Lin Ft $ $

13

Install new powder coated steel

bar & prefabricated panel

guardrail per plan and spec

45 Lin Ft $ $

14 Install new bubble-up boxes per

plan and spec 6 Ea $ $

15 Install new 8" SDR-35 storm

drain pipe per plan and spec 90 Lin Ft $ $

BID

C-4 (Addendum #1)

Item

No. ITEM QTY UNIT UNIT

COST TOTAL

16

Install new gypsum board ceiling

per plan and spec. (Add #1 –

quantity increased)

395 Sq Ft $ $

17 Install new pendant light fixture

per plan and spec 15 Ea $ $

18

Install new 24 ga. Pre-finished

metal parapet wall caps per plan

and spec

85 Lin Ft $ $

19 Install galvanized metal pipe jack

flashings per plan and spec 1 Ea $ $

20

Repair and install new gypsum

board over air barrier and paint

on interior wall behind new

clerestory storefront windows

(Add #1 – new bid item)

600 Sq Ft $ $

FILTER GALLERY SUBTOTAL: $

GENERAL CONDITIONS

1 General Conditions 1 Lump

Sum $

2 Contractor's Supervision 1 Lump

Sum $

3 Payment & Performance Bonds

and Insurance 1 Lump

Sum $

4 Project mobilization 1 Lump

Sum $

5 Pedestrian safety 1 Lump

Sum $

6 Temporary Construction Fencing 1 Lump

Sum $

7 Interior Dust & Debris Control

(Add #1 – new bid item) 1 Lump

Sum $

GENERAL CONDITIONS SUBTOTAL: $

BID SCHEDULE TOTAL

(Actiflo Bldg. + Filter Gallery + General Conditions): $

Bidder agrees to accept as full payment for Work proposed with the Bidding Documents

based upon the undersigned’s own estimate of quantities and costs and including sales,

consumer, use, other taxes, and overhead and profit.

Bidder (Company name):

BID

C-5 (Addendum #1)

By: Dated:

(Signature)

Name: Title:

ATTACHMENTS TO THIS BID

The following documents are attached to and made a condition of this Bid:

1. Required Bid security in the form of Bid Bond.

2. Information Required of Bidder.