THE WIRE · UPDATED 8:32 AM MDT No story is too small.
Official SourceWest Jordan

Sugar Factory Road Improvements (2200 West to 1750 West) - West Jordan City

Utah.News 1 source cited 1 primary Primary: westjordan.utah.gov Details

How this story was published

Published automatically from one public source cited; not yet reviewed by the desk. Tell us if something is wrong ↗

Primary source

westjordan.utah.gov — an official government, school or university source.

Utah.News publishes every story with the sources it was built from. Questions or a correction: corrections@utah.news.

Official source This story comes from an official government or institutional source.
Sugar Factory Road Improvements (2200 West to 1750 West) - West Jordan City
Photo via westjordan.utah.gov
Neighborhood meeting Oct. 28Residents are invited to drop in and meet with City leaders and staff to learn about the project, ask questions and share feedback before construction begins.When: Wednesday, Oct. 28, 6 to 7

The City of West Jordan is improving Sugar Factory Road between 2200 West and 1750 West. The project adds a new sidewalk, moves power lines underground and repaves the road, making it safer and more walkable for the neighborhood. Check this page for project updates, construction schedules and ways to share your questions.

Neighborhood meeting Oct. 28

Residents are invited to drop in and meet with City leaders and staff to learn about the project, ask questions and share feedback before construction begins.

When: Wednesday, Oct. 28, 6 to 7 p.m.

Where: West Jordan City Hall, Council Chambers (3rd floor), 8000 S. Redwood Road

No RSVP needed. [Download the meeting flyer (PDF)]

About the project

Sugar Factory Road doesn’t have a continuous sidewalk on its south side. This project closes that gap and gives people a safer place to walk. The City is doing the sidewalk, power line and paving work as one project, so the road is only torn up once.

What’s planned

New curb, gutter and sidewalk on the south side from 1950 West to 1750 West

Slight road widening

Overhead power lines on the south side moved underground

A fresh road surface (mill and overlay) from 2200 West to 1750 West

Project timeline

Design: Complete

Neighborhood meeting: Oct. 28, 2026

Construction start: Fall 2026

Estimated completion: Winter 2026

What to expect during construction

We’ll share more details as the schedule is set. Residents along the project area will receive notice before work begins near their homes. Driveway access will be maintained as much as possible, and we’ll give advance notice of any temporary closures.

Questions?

Email communications@westjordan.utah.gov.

Watch

Utah News

Article details

CategoryOfficial Source
CityWest Jordan
ToneNeutral
Report a problem with this story
What's off? Pick any that fit, or just write below.

Every report is read and checked against the story's sources. Your email, if you give one, is used only to contact you about this message and is never shown publicly. Please keep other personal details out of the text. Privacy