The Forest Street Overpass will open to traffic in mid-July, significantly ahead of its original completion estimates of late 2026 or early 2027. A ribbon-cutting ceremony is scheduled for Tuesday, July 7, at 9 a.m. at the top of the overpass on the east side.
Final construction details
While final preparations like the completion of a parapet wall will occur in the days following the ceremony, the road is expected to be fully open sometime during the following week.
Addressing railroad crossing delays
The project aims to address long-standing concerns regarding the railroad crossing on Forest Street. City leaders and emergency responders have noted that trains have caused delays for response vehicles.
Importance of emergency response time
Brigham City Fire Chief Brandon Thueson stated that time is the most valuable commodity in the fire service, noting that minutes can change survival rates during emergencies.
Funding through railroad fuel tax
The overpass project was initiated after efforts to reach an agreement with the railroad were unsuccessful. Utah State Representative Joel Ferry and Utah State Senator Scott Sandall sponsored legislation to impose a fuel tax on railroads to fund infrastructure projects that reduce train impacts on cities.
First project using new tax
The Forest Street Overpass is the first project in Utah funded by that specific fuel tax. Brigham City Mayor DJ Bott expressed appreciation for state representatives and city leaders who secured funding without using city revenues, noting excitement about opening the road ahead of schedule.
Road closure and ceremony details
Forest Street has been closed to all traffic since January 2025. Members of the public are invited to attend the ribbon-cutting ceremony and are encouraged to use the parking lot near the swimming pool.